Screw Compressor Units: Principles, Design and Selection - Essential Guide for Refrigeration Beginners
2025-02-26
System Schematic Diagram:
Refrigerant Circulation:
Ejector Enthalpy - boosting:
For the same compressor, under the same evaporation and condensation temperatures, the COP value increases by 6% - 8%.
At the same time, the compressor's exhaust temperature drops by 1 - 2 °C, improving the compressor's operating conditions and enhancing its operating reliability.
Ejector Oil Return:
Design and Selection:
Selection Process: Calculate the load of each individual space → Select the terminal → Select the main unit → Check the cooling/heating load → Confirm.
Indoor Load Calculation: Indoor load (W) = Room area (m²) × Unit load (W/m²)
Note: The selection of load indicators needs to consider the actual on - site situation.
Terminal Selection: Select the appropriate terminal form according to conditions such as load, noise, and installation space.
Main Unit Selection: Generally, select the main unit according to a simultaneous - use coefficient of 0.7 - 0.8 for all terminals. When choosing the main unit, it is preferred to select 2 units, and there is no need to consider a backup.
Heating Load Check: It is necessary to check the heating load if there is a heating demand, and no check is required if there is no such demand.
After selecting the main unit and the terminal, check the heating load. If it is satisfied, the selection can be directly confirmed. If not, select the terminal and the main unit according to the heating load and then check the cooling load until both the cooling and heating loads meet the requirements.
Selection Case:
Example: Building Conditions: The construction area of an office building is 13000 m², and the air - conditioned area is 12000 m². Among them, the area of the large conference room is 800 m², the area of the small conference room is 2000 m², and the area of the office area is 9200 m². There is a fresh - air demand and no heating demand.
A. Calculate the cooling load.
a. Estimate according to the air - conditioning cooling load method:
Large conference room: 800 × 200 (W/m²) = 160000W = 160kW
Small conference room: 2000 × 240 (W/m²) = 480000W = 480kW
Office area: 9200 × 120 (W/m²) = 1104000W = 1104kW
Total: 160kW + 480kW + 1104kW = 1744kW
Load when selecting the main unit: 1744kW × 0.70 = 1220.8kW
b. Estimate according to the construction - area method: 13000 × 98W = 1274kW
c. Based on the calculation results of a and b, the cooling load is calculated as 1274kW.
B. Initially select the unit model and quantity:
Check the product design and selection manual and refer to the design requirements.
Installation Key Points:
Installation Environment: The unit should be kept away from fire sources and flammable materials. If it is installed alongside heat - generating devices such as boilers, pay full attention to the impact of heat radiation.
Select a place with a room temperature below 45 °C and good ventilation. Outdoor or open - air installation and storage are not allowed, and installation in an environment with corrosive gases is not permitted.
Choose a place with less dust.
The site should have good lighting for easy maintenance and inspection.
To meet the needs of maintaining, repairing, and cleaning the heat - exchange tubes of the evaporator and condenser, there must be sufficient space for tube - pulling at either end of the unit. In the length direction, it should be equivalent to the length of the evaporator and condenser of the unit.
To facilitate the lifting and maintenance of the machine, leave the space required for the installation, operation, and maintenance of the unit.
The area around the unit and the entire machine room should be fully drainable.
Reserve maintenance space during installation:
Installation Foundation Diagram:
The installation foundation of the unit must be a cement or steel structure. It should be able to bear the operating weight of the machine, and its upper surface should be level. It is better to reserve a drainage groove in the installation foundation of the unit.
Refer to the installation foundation schematic diagram of the unit and place it accurately on the foundation.
Install steel plates and vibration - proof rubber pads. After the unit is installed in place together with the anchor bolts, perform secondary grouting. The anchor bolts are generally installed to protrude approximately 100mm above the installation plane.
Hoisting Schematic Diagram: When hoisting, please operate strictly in accordance with the hoisting markings on the unit.
Refrigerant Circulation:
Ejector Enthalpy - boosting:
For the same compressor, under the same evaporation and condensation temperatures, the COP value increases by 6% - 8%.
At the same time, the compressor's exhaust temperature drops by 1 - 2 °C, improving the compressor's operating conditions and enhancing its operating reliability.
Ejector Oil Return:
Design and Selection:
Selection Process: Calculate the load of each individual space → Select the terminal → Select the main unit → Check the cooling/heating load → Confirm.
Indoor Load Calculation: Indoor load (W) = Room area (m²) × Unit load (W/m²)
Note: The selection of load indicators needs to consider the actual on - site situation.
Terminal Selection: Select the appropriate terminal form according to conditions such as load, noise, and installation space.
Main Unit Selection: Generally, select the main unit according to a simultaneous - use coefficient of 0.7 - 0.8 for all terminals. When choosing the main unit, it is preferred to select 2 units, and there is no need to consider a backup.

Heating Load Check: It is necessary to check the heating load if there is a heating demand, and no check is required if there is no such demand.
After selecting the main unit and the terminal, check the heating load. If it is satisfied, the selection can be directly confirmed. If not, select the terminal and the main unit according to the heating load and then check the cooling load until both the cooling and heating loads meet the requirements.
Selection Case:
Example: Building Conditions: The construction area of an office building is 13000 m², and the air - conditioned area is 12000 m². Among them, the area of the large conference room is 800 m², the area of the small conference room is 2000 m², and the area of the office area is 9200 m². There is a fresh - air demand and no heating demand.
A. Calculate the cooling load.
a. Estimate according to the air - conditioning cooling load method:
Large conference room: 800 × 200 (W/m²) = 160000W = 160kW
Small conference room: 2000 × 240 (W/m²) = 480000W = 480kW
Office area: 9200 × 120 (W/m²) = 1104000W = 1104kW
Total: 160kW + 480kW + 1104kW = 1744kW
Load when selecting the main unit: 1744kW × 0.70 = 1220.8kW
b. Estimate according to the construction - area method: 13000 × 98W = 1274kW
c. Based on the calculation results of a and b, the cooling load is calculated as 1274kW.
B. Initially select the unit model and quantity:
Check the product design and selection manual and refer to the design requirements.
Installation Key Points:
Installation Environment: The unit should be kept away from fire sources and flammable materials. If it is installed alongside heat - generating devices such as boilers, pay full attention to the impact of heat radiation.
Select a place with a room temperature below 45 °C and good ventilation. Outdoor or open - air installation and storage are not allowed, and installation in an environment with corrosive gases is not permitted.
Choose a place with less dust.
The site should have good lighting for easy maintenance and inspection.
To meet the needs of maintaining, repairing, and cleaning the heat - exchange tubes of the evaporator and condenser, there must be sufficient space for tube - pulling at either end of the unit. In the length direction, it should be equivalent to the length of the evaporator and condenser of the unit.
To facilitate the lifting and maintenance of the machine, leave the space required for the installation, operation, and maintenance of the unit.

The area around the unit and the entire machine room should be fully drainable.
Reserve maintenance space during installation:
Installation Foundation Diagram:
The installation foundation of the unit must be a cement or steel structure. It should be able to bear the operating weight of the machine, and its upper surface should be level. It is better to reserve a drainage groove in the installation foundation of the unit.
Refer to the installation foundation schematic diagram of the unit and place it accurately on the foundation.
Install steel plates and vibration - proof rubber pads. After the unit is installed in place together with the anchor bolts, perform secondary grouting. The anchor bolts are generally installed to protrude approximately 100mm above the installation plane.
Hoisting Schematic Diagram: When hoisting, please operate strictly in accordance with the hoisting markings on the unit.

Related Articles
- Why is the Evaporator Position Higher than the Compressor? Several Key Points of Oil Return in the Refrigeration System!
- Installation Project and Usage Introduction of Parallel Compressor Units in Cold Storage
- What Are the Common Problems of Oil Return in Compressors?
- Have You Encountered These Main Reasons for the Burning of Refrigeration Compressor Windings?
- Don't You Know These Four Aspects of Compressor Protection?
- 62 Compressor Questions: Read and Become an Expert!
- What to Do When the Compressor of a [Refrigerated and Frozen Display Cabinet] Unit Makes Abnormal Noises?
- Did You Know? Any Incompatibility between Base Oil and Refrigerant Could Destroy a Refrigeration Compressor
- Simple and Understandable Installation Method of Vibration - isolation Tubes for Refrigeration Compressors
- What Should Be Done When These Problems Occur in the Semi-hermetic Piston Compressor of the Cold Storage?
- A Complete Guide to the Operation, Malfunctions and Repair Methods of Dry Screw Refrigeration Compressors!
- Operation: Analysis of 20 Major Faults of Screw Compressors!
- Analyzing the Advantages and Disadvantages of 5 Types of Compressors in Cold Chain Technology
- Teach You to Completely Get Rid of the Surge Phenomenon of the Centrifugal Refrigeration Compressor
- Analysis of Causes for Exhaust Malfunctions of Screw - type Chiller Compressors
- Structure and Common Faults of Hermetic Compressors
- Why Does the Air - conditioner Compressor Stop Running in Less Than 1 Minute?
- Do You Know the Precautions for Using Rotary Refrigeration Compressors?
